Construction Update – Pier 2/3
- Structural timber rectification works and the installation of structural steel are continuing.
Construction Update – Wharf 4/5
- Rectification to the wharf sub-structure is ongoing.
- Construction of the internal spaces in each of the tenancy areas is taking shape. Services installations have also been ongoing in all tenancy areas.
- Rectification works to the roof, western façade and balcony are ongoing.
Upcoming work expected over the next month:
- Continuing the timber rectification works and structural steel installations at Pier 2/3.
- Continuing the rectification works for the Wharf 4/5 sub-structure.
- Completion of roof works on Wharf 4/5 before installing new solar panels.
- Commencing works to install the external gantries and stairs at Wharf 4/5.
- Continuing façade rectification and balcony works on the western side of Wharf 4/5.
- All areas in Wharf 4/5 are progressively being fit out, with cabling being terminated to get ready for testing and commissioning.