August 2020 construction update

Construction Update – Pier 2/3

  • Structural timber rectification works and the installation of structural steel are continuing.

Construction Update – Wharf 4/5

  • Rectification to the wharf sub-structure is ongoing.
  • Construction of the internal spaces in each of the tenancy areas is taking shape. Services installations have also been ongoing in all tenancy areas.
  • Rectification works to the roof, western façade and balcony are ongoing.

Upcoming work expected over the next month:

  • Continuing the timber rectification works and structural steel installations at Pier 2/3.
  • Continuing the rectification works for the Wharf 4/5 sub-structure.
  • Completion of roof works on Wharf 4/5 before installing new solar panels.
  • Commencing works to install the external gantries and stairs at Wharf 4/5.
  • Continuing façade rectification and balcony works on the western side of Wharf 4/5.
  • All areas in Wharf 4/5 are progressively being fit out, with cabling being terminated to get ready for testing and commissioning.